Henry County approved its 2023 LMIG application at the February 7 board meeting. LMIG is an annual grant administered by Georgia DOT. The grant represents a primary source of funding to resurface county roads.
In 2023, the county will receive $2.3 million from Georgia DOT. When considered with the requisite local match, Henry County has $3 million in this year’s budget. This amount will resurface an estimated six miles of roadway.
Henry County 2023 LMIG
The LMIG program is a statewide program. It allocates available funding based on population and road mileage. For counties, this considers the unincorporated population only. Each city receives LMIG funding separate from Henry County. The list below is reflective of county funds only.
For 2023, the majority of streets Henry County will resurface are located within subdivisions.
District I
Grove Spring subdivision
- Grove Spring Road, Locust Road to Shelley Lane – 0.4 miles
- Indian Spring Drive, end to end – 0.4 miles
- Shelley Lane, Indian Spring Dr to end – 0.4 miles
District II
- Flakes Road, Flat Rock Road to Old Conyers Road – 0.6 miles (cost share with district III)
- Cook Drive, Clark Drive to Flakes Mill Road – 0.6 miles
District III
- Flakes Road, Flat Rock Road to Old Conyers Road – 0.6 miles (cost share with district II)
Deerfield Plantation subdivision
- Fawn Crossing, Thicket Trail to end – 0.03 miles
- Thicket Trail, Highway 155 to end – 0.4 miles
Nails Creek at The Farm subdivision
- Nails Creek Court, Nails Creek Trail to end – 0.1 miles
- Nails Creek Trail, The Farm Road to end – 0.3 miles
Chimney Ridge subdivision
- Oak Ridge Court, Flat Rock Road to end – 0.1 miles
- Smoke Ridge Court, Flat Rock Road to end – 0.1 miles
District IV
Dickerson Cove subdivision
- Dickerson Cove Drive, Millers Mill Road to end – 0.3 miles
Rosewood subdivision
- Rosebud Lane, Jonesboro Road to Rosewood Drive – 0.2 miles
- Rosehill Drive, Rosewood Dr to Rosewood Dr – 0.2 miles
- Rosewood Drive, Jonesboro Road to Rosehill Dr – 0.4 miles
District V
Gates of Rowanshyre subdivision
- Rowanshyre Way, Mount Carmel Road to Rowanshyre Circle – 0.04 miles
- Rowanshyre Circle, end to end – 0.6 miles
Legends of Rowanshyre subdivision
- Shyre Lake Lane, end to end – 0.1 miles
- Westwinds Trail, Windward Hills to Windward Hills – 0.1 miles
- Windward Hills, Mill Road to Shyre Lake Lane – 0.4 miles
Resurfacing Contract
Henry County typically considers bids for road resurfacing in March. Generally, the board considers contract award in April. This year, the county utilized a technical scoring when selecting which streets to resurface. An outside consultant conducted the evaluation beginning in 2020.
The technical scoring is available in its entirety on the county website (PDF link – 48 pages). This includes a ranking for each county-maintained road.
Featured image shows road resurfacing. Georgia DOT photo.