Public Works Director Ron Burckhalter gave an update to the Board at the March 19 Commission meeting regarding progress on the Lake Dow Rd. project.
Burckhalter advised that the county has contracted with a different consultant using a new design to move the project forward.
The consultants will use reinforced concrete pipe instead of the original plan to use pre-cast boxes. He said the pipes will be ordered by the end of the week and are available locally under contract.
Interim Stormwater Director Roque Romero said that all the work will be completed by Henry County crews and that Stormwater officials are currently in conversations with the Homeowners Associations that own the lakes, to discuss lowering the lake in order for construction to commence.
This update is reprinted from Henry County Communications. Sign up for the county’s newsletter to receive updates via email.