GDOT Begins the Procurement Process for Bethlehem Road Exit

Photo showing March 2023 concept layout for the I-75 interchange at Bethlehem Road (Georgia DOT photo).
I-75 at Bethlehem Road interchange, March 2023 concept. (Georgia DOT photo)

Georgia DOT has officially started the procurement process for the I-75 at Bethlehem Road exit. The state plans to hire a contractor by the end of 2025. The project will build a new interstate exit between McDonough and Locust Grove.

I-75 at Bethlehem Road Exit Procurement

Georgia DOT published the Public Notice Advertisement (PNA) on February 5, 2025. This includes GDOT’s anticipated schedule for the Bethlehem Road exit procurement:

  • March 2025 – Industry Forum & Contractor Meetings
  • April 2, 2025 – GDOT issues Request for Qualifications (RFQ)
  • May 8, 2025 – RFQ submission deadline
  • June 2, 2025 – GDOT announces project finalists
  • June 5, 2025 – GDOT issues Request for Proposals (RFP) to finalists
  • October 2, 2025 – RFP submission deadline
  • October 24, 2025 – GDOT letting (contract award)

The above schedule may change or have adjustments if needed.

The state DOT is using a design-build process for the project. This means they will hire a project team involving both a design firm and general contractor. The team will then finalize the project’s design before construction begins. More information about design-build projects is on the state DOT website.

The selected design-build team will coordinate the project with Georgia DOT and the SR 42 bridge replacement. Procurement for the bridge replacement project is also underway this year; it too is a design-build contract.

About the Project

Georgia DOT shared the project’s concept layout during an open house in spring 2023. Some key elements of the design include the following:

Photo showing March 2023 concept layout for the I-75 interchange at Bethlehem Road (Georgia DOT photo).
I-75 at Bethlehem Road interchange, March 2023 concept. (Georgia DOT photo)
  • A new four-lane road located south of the existing Bethlehem Road, between Greenwood Industrial and SR 42,
  • On- and off-ramps from I-75 to new Bethlehem Road,
  • four roundabouts, to include new Bethlehem Road at Greenwood, new Bethlehem Road at SR 42, and I-75 north & south off-ramps, and
  • three new bridges, to include Bethlehem Road over I-75, Bethlehem Road over Bethlehem Bottoms Creek, and I-75 Northbound off-ramp.

Henry County formally began to study the idea for a new interstate exit in 2014. The federal government gave its approval in 2018. Georgia DOT assumed the lead to build the new exit around 2020-21. Construction on the new exit could begin as early as 2026. It should be complete around 2029-2030.

The latest cost estimate for the project has $232 million for construction, and $261 million in total costs. Henry County contributed $5 million and Locust Grove contributed $1 million towards its construction. The remainder is state and federal funds.

Featured image shows the I-75 at Bethlehem Road concept. Georgia DOT photo.

About Clayton 1796 Articles
Clayton Carte is the founder and owner of The Henry Reporter. He founded the site in 2017 to highlight transportation projects. Over time, he began covering other topics like new development so residents can best know what’s happening in our community.