Bridge work scheduled on SR 81 replacement

Photo of SR 81 bridge over South River (Georgia DOT photo)

Georgia DOT shared an update on January 20 about the upcoming bridge replacement on state route 81 over the South River. GDOT awarded a contract to replace the existing bridge in July.

The existing bridge was built in 1948. The project will utilize an offsite detour during construction.

Project Update

GDOT expects Wright Brothers Construction Company to mobilize next week, the week of January 25, and begin clearing February 1. The detour should begin by mid-March and be complete by December 2021 barring any setbacks.

The assigned state highway detour totals 34 miles. The detour follows state routes 20 and 212 from downtown McDonough to Zion Baptist Church before turning towards SR 81 at 212. State route 36 is also an option to traverse the South River.

GDOT selected the off-site detour method and duration to reduce environmental and property impacts, while expediting construction and reducing cost.

Follow Georgia DOT – East on Facebook for the latest updates during construction. Henry County projects are traditionally covered by Georgia DOT – West, but this project is an exception due to its location on the Henry / Newton County border. Newton County projects are grouped under the east district.

Bridge Replacement

The project was awarded to Wright Brothers Construction Company, Inc. of Charleston, TN in the amount of $4,299,065.91. When complete, the new bridge will be 345’ in length and feature a deck width of 43.25’ including an eight foot shoulder on each side. By comparison, the existing bridge is 27’ wide.

Credit for the featured image to Georgia DOT.

About Clayton 1688 Articles
Clayton Carte is the founder and owner of The Henry Reporter. He founded the site in 2017 to highlight transportation projects. Over time, he began covering other topics like new development so residents can best know what’s happening in our community.

Be the first to comment

Leave a Reply